Volgograd Region Governor inspected the progress of the construction of an overpass at the entrance to Volgograd from highway M-6 "Caspian" 2nd December 2013
02.12.2013
November 30, 2013 Sergey Bozhenov visited the construction site of "Volgomost" in the village Gumrak Volgograd region.
In the exit meeting was also attended by the head of Mostootryad № 57 of OJSC "Volgomost" Alexander Plotnikov, as well as representatives of subcontractors.
"Today overpass is 100% complete, the road portion of the project is executed in an amount sufficient to trigger movement. Who makes the final work to ensure traffic safety on the overpass: installation of signage, striping, installation of barrier fencing", - said Alexander Plotnikov. Overpass under construction is the key object of the project, the launch of the movement on it will solve one of the major traffic problems Volgograd - traffic jams on the way to the international airport. Now residents and visitors are forced to waste time standing idle in a closed railroad crossing. New transport shift would get to the airport and in the opposite direction, passing the railroad tracks.
"Today we can say that the object, whose discoveries Rotor been waiting for, is almost ready. Until the end of December will open the first part - two lanes, and in the spring when weather conditions permit, the builders will do the rest. The main thing - it's the quality of work, contractor fulfills its obligations clearly" - said the Governor Sergei Bozhenov .
For reminding: the construction of the object of "Volgomost" leads to September 2012, its total linear length of 1.2 km. The facility includes a viaduct length of 155 meters, the network transport interchanges, stairs and walkways for pedestrians.
November 30, 2013 Sergey Bozhenov visited the construction site of "Volgomost" in the village Gumrak Volgograd region.
In the exit meeting was also attended by the head of Mostootryad № 57 of OJSC "Volgomost" Alexander Plotnikov, as well as representatives of subcontractors.
"Today overpass is 100% complete, the road portion of the project is executed in an amount sufficient to trigger movement. Who makes the final work to ensure traffic safety on the overpass: installation of signage, striping, installation of barrier fencing", - said Alexander Plotnikov. Overpass under construction is the key object of the project, the launch of the movement on it will solve one of the major traffic problems Volgograd - traffic jams on the way to the international airport. Now residents and visitors are forced to waste time standing idle in a closed railroad crossing. New transport shift would get to the airport and in the opposite direction, passing the railroad tracks.
"Today we can say that the object, whose discoveries Rotor been waiting for, is almost ready. Until the end of December will open the first part - two lanes, and in the spring when weather conditions permit, the builders will do the rest. The main thing - it's the quality of work, contractor fulfills its obligations clearly" - said the Governor Sergei Bozhenov .
For reminding: the construction of the object of "Volgomost" leads to September 2012, its total linear length of 1.2 km. The facility includes a viaduct length of 155 meters, the network transport interchanges, stairs and walkways for pedestrians.